Crossing at Eastoke Corner
2010

The ground surrounding the track was dug up by volunteers of the HSR
Photo: K. Edwards

Check rails were then put in place
Photo: K. Edwards

Wooden posts were put in the ground to mark out where the concrete
had to go
Photo: A. Rose

The concrete was then poured into the track bed and levelled out
smoothly by HSR volunteers
Photo: A. Rose

The concrete was then smoothed out and the check rails were
cleared to make sure the train could easily go through it
Photo: A. Rose

'Edwin' was used as a test train to make sure the check rails were clear
Photo: K. Edwards

After the concrete had set the passenger train was then able to go
through it and into Eastoke Corner station
Photo: Keith Edwards

This picture shows the digger at work preparing the area for the
new road
Photo: Andrew Rose

This picture shows the concrete being laid out to form the new road
Photo: Andrew Rose

With one half of the road completed, work starts on the other half
Photo: Andrew Rose

The concrete edging was then put in place either side
Photo: Andrew Rose

This picture shows most of the tarmac in place on the 23rd May
Photo: Andrew Rose

This picture shows most of the tarmac in place on the 23rd May
Photo: Andrew Rose

The tarmac is almost finished and the posts are in place for signage
Photo: Andrew Rose

The wooden bollards are being installed and the crossing hopes
to be open to road traffic by the weekend (29/30)
Photo: Andrew Rose
|